PCBA Purchasing Cost Analysis and Price Variance Method

ShareFacebookXLinkedInPinterestTelegram

When we analyze procurement costs using a procurement cost index and by looking at related commodity prices, the main goal is to see, at the company level, whether changes in PCBA (parts and materials supplied) procurement cost make the company more competitive in the external market or less competitive. From inside the company, changes in purchase unit price and in purchase quantity can both change procurement cost. How do we tell which factor matters more? The worked example below separates quantity and price effects using explicitly stated inputs.

1. Controllable Factors

Consider a hypothetical material A, using the displayed unit prices as exact inputs. Its previous price is $1.30 per unit and its current price is $1.37. The previous quantity is 100 units and the current quantity is 110 units. The following decomposition uses those values, rather than unstated unrounded prices.

The previous purchase amount, A, is $130.00 ($1.30 × 100). The current amount, A + B + C + D, is $150.70 ($1.37 × 110), an increase of $20.70. The quantity-only component B is $13.00 ($1.30 × 10), the price-only component C is $7.00 ($0.07 × 100), and the interaction component D is $0.70 ($0.07 × 10). Their sum is $20.70. An attribution convention must state whether D is included in the quantity or price effect.

Scroll horizontally to view all columns.

Material A cost decomposition (USD)
ComponentCalculationAmount (USD)
A: previous amount1.30 × 100130.00
B: quantity only1.30 × (110 − 100)13.00
C: price only(1.37 − 1.30) × 1007.00
D: interaction(1.37 − 1.30) × (110 − 100)0.70
Current amountA + B + C + D150.70

Here we need a common attribution rule used in management data analysis: attribute to the controllable factor.

A company’s “controllable factors” are those that you can more easily change by your own efforts. That means, if you make the same effort to change two factors, the factor that produces the larger effect is the company’s “controllable factor.” Controllability is relative.

When you analyze how different factors cause a result, sometimes one result can be explained by two or more factors and each explanation looks reasonable. If you must pick one factor, choose the factor that is more controllable by you. Why pick this? Because the point of management data analysis is to act on the results to get better business outcomes. If you enlarge the role of the controllable factor, you point to the action that gives the largest return on your effort. That gives a clearer direction for management to act.

2. Quantity-Price Allocation

For most companies, the amount of materials used in PCBA work is mainly linked to production volume. To change usage, you normally need design changes or process improvements. That is hard. Compared with changing quantity, a company can usually do more to affect the purchase price. So, relative to quantity, purchase unit price is the more “controllable factor.” In the convention used here, the interaction component D is assigned to the purchase price effect. Of course, some companies can control quantity better than price. In that case, use the real situation for that company.

With the interaction assigned to price, the quantity effect is B = $13.00 and the price effect is C + D = $7.70. Together they reconcile to the total increase of $20.70. This is an attribution convention, not a claim that only price caused the interaction.

Can we split D evenly between “quantity” and “unit price”? We usually do not do that. Management data analysis is not the same as scientific analysis. Management analysis does not pursue perfect precision. It does not need perfect fairness either. The goal is usefulness. The goal is to give management a clear direction. If a simple method gives a clear direction, it is better than a more complex method that is only slightly more precise.

If we split D in half, the result may look more precise or more fair. But that also makes the algorithm more complex and harder to understand. It does not give a better direction for management action. In other words, that extra precision is not useful.

Back to the chosen quantity-price allocation method for purchase cost change. In table form, it looks like this:

Key Definitions

  • LQ: Last Quantity (previous period purchase quantity)
  • CQ: Current Quantity (current period purchase quantity)
  • LP: Last Price (previous period purchase unit price)
  • CP: Current Price (current period purchase unit price)
  • PQV: Purchasing Quantity Variance
  • PPV: Purchasing Price Variance

Illustrative inputs retained from the example; amounts below are recalculated from the displayed unit prices. All monetary values in this table are RMB. Positive effects increase cost; negative effects reduce cost.

Scroll horizontally to view all columns.

Quantity-price variance using exact displayed inputs
ItemCategorySupplierPrevious unit price LPCurrent unit price CPPrevious quantity LQCurrent quantity CQPrevious amountCurrent amountCost changeQuantity effect PQVPrice effect PPVPrice effect / previous amount
A001BearingSupplier A59.6356.3032439119,320.1222,013.302,693.183,995.21-1,302.03-6.74%
A002BearingSupplier A37.1535.3861563422,847.2522,430.92-416.33705.85-1,122.18-4.91%
A003BearingSupplier A24.6123.8972580017,842.2519,112.001,269.751,845.75-576.00-3.23%
A004BearingSupplier A17.2315.9682370014,180.2911,172.00-3,008.29-2,119.29-889.00-6.27%
A005BearingSupplier A45.7444.3652854724,150.7224,264.92114.20869.06-754.86-3.13%
A006BearingSupplier B22.9022.232282905,221.206,446.701,225.501,419.80-194.30-3.72%
A007BearingSupplier B46.5742.3597491145,359.1838,580.85-6,778.33-2,933.91-3,844.42-8.48%
Total148,921.01144,020.69-4,900.323,782.47-8,682.79-5.83%

Quantity-Price Analysis Template for Procurement Cost Change

Key Formulas

  • Quantity variance (PQV) = Last Price (LP) × (Current Quantity (CQ) − Last Quantity (LQ))
  • Price variance (PPV) = (Current Price (CP) − Last Price (LP)) × Current Quantity (CQ)

Using the displayed inputs, total cost changes from RMB 148,921.01 to RMB 144,020.69, a reduction of RMB 4,900.32 (3.29% of the previous total). The quantity effect is +RMB 3,782.47 (+2.54%), and the price effect is −RMB 8,682.79 (−5.83%). These two effects sum exactly to the total change before percentage rounding. Individual price effects range from −3.13% to −8.48% of each item’s previous purchase amount. This is a worked calculation, not verified procurement data for FLJ PCB.

Using this template makes it simple to do quarterly or yearly quantity-price attribution analysis for procurement cost change. The template can also clearly show, from either the quantity side or the price side, which materials should be the next focus. For the supply side, especially for the purchasing department, more effort is needed on the price side.

3. Summary

Above we described how to allocate and analyze quantity and price when total procurement cost changes. We also described a common attribution principle in management data analysis: attribute to the controllable factor. We stressed that the main goal of management analysis is to give action directions for business management, not to be as precise as possible. Usefulness is the most important thing.

When learning an analysis tool, more important than knowing how to use it is understanding the analysis method behind it. The real value lies not in the tool itself but in the ability to use the tool well.